FAQs
Do we have the money?
This $3 million project has been fully funded by the Victorian Government and the Australian Government’s Local Roads and Community Infrastructure Fund.
When will it be finished?
The completion of the project is scheduled to coincide with the end of the 2025 Wimmera Football and Netball League season, ensuring the facility is ready for use in the following season.
Is the pavilion project still on track?
The new netball pavilion project is very much on track.
The tender process midway through 2024 was not without its challenges. Rising construction industry costs necessitated three separate calls for tenders.
In July, Horsham company Locks Constructions was awarded the contract to build the new pavilion, bringing the much-anticipated project a step closer to reality.
How is HRCC working with HFNC to ensure disruption is minimalised?
Council holds monthly meetings with the club and other City Oval stakeholders, to ensure disruption is minimised during the construction period.